Records not loaded — Delivery tracking (second instance)
Connection lost. Figures on this page do not include the latest data from Delivery tracking (second instance) (DT-C). Use Retry on this source in Administration → Data sources.
On-time rate
Every milestone with a plan baseline due date before the reporting cutoff, including earlier months, counting those completed on or before that due date. Incomplete or late milestones are misses.
As of 20 Oct 2026 (cutoff)
Definition and formula
Definition v1
- Formula
- On-time rate = Met ÷ Due (all milestones due before the cutoff; numerators and denominators pooled, never averaged)
- Target
- 90%
- Thresholds
- · No status threshold — target only
Comparison and source
Previous month and the systems behind the number.
- Previous month (Sept 2026)
- 85% → 82%
- Data source
- Delivery tracking (main)Loaded at09:58Data as of20 Oct 2026Delivery tracking (second instance)Loaded at09:13Data as of20 Oct 2026Stale
Provenance and audit
Where this number came from, and which published versions produced it.
Quality: Error — Records not loaded from Delivery tracking (second instance). The retained values below are the previous snapshot.
- Reporting cutoff
- 20 Oct 2026
- Last calculated
- 20 Oct 2026, 10:00
- Definition version
- Definition v1
- Threshold version
- Not applicable
- Plan baseline version
- Plan baseline v1, Plan baseline v2
- Configuration version
- Version 1
- Contributing records
- 74
- Records excluded
- 1
Exclusion reasons: Held for review — no plan baseline due date in effect
- Delivery tracking (main) · batch DT-MAIN:initial (version 1) · Loaded at 2 minutes ago · Data as of 20 Oct 2026
- Delivery tracking (second instance) · batch DT-C:initial (version 1) · Loaded at 47 minutes ago · Data as of 20 Oct 2026 · Stale
Full provenance for each record is on its record page.
Contributing records
These records reproduce the total. Met / Due.
| Record | Project | Met / Due | Detail |
|---|---|---|---|
| Core network cutover milestone 1DT-MAIN · DT-201-M001 | Core network cutover | Met | Due 8 Apr 2026 · Completed 7 Apr 2026 |
| Internal tooling refresh milestone 2DT-MAIN · DT-202-M002 | Internal tooling refresh | Met | Due 15 Apr 2026 · Completed 14 Apr 2026 |
| Core network cutover milestone 3DT-MAIN · DT-201-M003 | Core network cutover | Met | Due 6 May 2026 · Completed 5 May 2026 |
| Internal tooling refresh milestone 4DT-MAIN · DT-202-M004 | Internal tooling refresh | Missed | Due 12 May 2026 · Completed 15 May 2026 |
| Core network cutover milestone 5DT-MAIN · DT-201-M005 | Core network cutover | Met | Due 20 May 2026 · Completed 19 May 2026 |
| Core network cutover milestone 6DT-MAIN · DT-201-M006 | Core network cutover | Met | Due 5 Jun 2026 · Completed 4 Jun 2026 |
| Internal tooling refresh milestone 7DT-MAIN · DT-202-M007 | Internal tooling refresh | Met | Due 14 Jun 2026 · Completed 13 Jun 2026 |
| Core network cutover milestone 8DT-MAIN · DT-201-M008 | Core network cutover | Met | Due 22 Jun 2026 · Completed 21 Jun 2026 |
| Core network cutover milestone 9DT-MAIN · DT-201-M009 | Core network cutover | Met | Due 7 Jul 2026 · Completed 6 Jul 2026 |
| Internal tooling refresh milestone 10DT-MAIN · DT-202-M010 | Internal tooling refresh | Missed | Due 16 Jul 2026 · Completed 19 Jul 2026 |
| Core network cutover milestone 11DT-MAIN · DT-201-M011 | Core network cutover | Met | Due 21 Jul 2026 · Completed 20 Jul 2026 |
| Core network cutover milestone 12DT-MAIN · DT-201-M012 | Core network cutover | Met | Due 4 Aug 2026 · Completed 3 Aug 2026 |
| Internal tooling refresh milestone 13DT-MAIN · DT-202-M013 | Internal tooling refresh | Missed | Due 11 Aug 2026 · Completed 14 Aug 2026 |
| Core network cutover milestone 14DT-MAIN · DT-201-M014 | Core network cutover | Met | Due 19 Aug 2026 · Completed 18 Aug 2026 |
| Core network cutover milestone 15DT-MAIN · DT-201-M015 | Core network cutover | Met | Due 9 Sept 2026 · Completed 8 Sept 2026 |
| Internal tooling refresh milestone 16DT-MAIN · DT-202-M016 | Internal tooling refresh | Missed | Due 17 Sept 2026 · Completed 20 Sept 2026 |
| Core network cutover milestone 17DT-MAIN · DT-201-M017 | Core network cutover | Met | Due 23 Sept 2026 · Completed 22 Sept 2026 |
| Internal tooling refresh milestone 18DT-MAIN · DT-202-M018 | Internal tooling refresh | Met | Due 9 Oct 2026 · Completed 8 Oct 2026 |
| Core network cutover milestone 19DT-MAIN · DT-201-M019 | Core network cutover | Missed | Due 12 Oct 2026 · Completed 15 Oct 2026 |
| Core switch cutoverDT-MAIN · DT-201-M020 | Core network cutover | Missed | Due 6 Oct 2026 · Completed — |
| Customer data platform milestone 25DT-MAIN · DT-301-M025 | Customer data platform | Met | Due 5 Apr 2026 · Completed 4 Apr 2026 |
| Customer portal milestone 26DT-MAIN · DT-302-M026 | Customer portal | Met | Due 12 Apr 2026 · Completed 11 Apr 2026 |
| Contact centre integration milestone 27DT-MAIN · DT-303-M027 | Contact centre integration | Met | Due 18 Apr 2026 · Completed 17 Apr 2026 |
| Customer data platform milestone 28DT-MAIN · DT-301-M028 | Customer data platform | Met | Due 6 May 2026 · Completed 5 May 2026 |
| Customer portal milestone 29DT-MAIN · DT-302-M029 | Customer portal | Met | Due 13 May 2026 · Completed 12 May 2026 |
| Contact centre integration milestone 30DT-MAIN · DT-303-M030 | Contact centre integration | Met | Due 19 May 2026 · Completed 18 May 2026 |
| Customer data platform milestone 31DT-MAIN · DT-301-M031 | Customer data platform | Met | Due 7 Jun 2026 · Completed 6 Jun 2026 |
| Customer portal milestone 32DT-MAIN · DT-302-M032 | Customer portal | Missed | Due 14 Jun 2026 · Completed 3 Jul 2026 |
| Contact centre integration milestone 33DT-MAIN · DT-303-M033 | Contact centre integration | Met | Due 20 Jun 2026 · Completed 19 Jun 2026 |
| Customer data platform milestone 34DT-MAIN · DT-301-M034 | Customer data platform | Met | Due 8 Jul 2026 · Completed 7 Jul 2026 |
| Customer portal milestone 35DT-MAIN · DT-302-M035 | Customer portal | Missed | Due 15 Jul 2026 · Completed 18 Jul 2026 |
| Contact centre integration milestone 36DT-MAIN · DT-303-M036 | Contact centre integration | Met | Due 21 Jul 2026 · Completed 20 Jul 2026 |
| Customer data platform milestone 37DT-MAIN · DT-301-M037 | Customer data platform | Met | Due 9 Aug 2026 · Completed 9 Aug 2026 |
| Customer portal milestone 38DT-MAIN · DT-302-M038 | Customer portal | Missed | Due 16 Aug 2026 · Completed 19 Aug 2026 |
| Contact centre integration milestone 39DT-MAIN · DT-303-M039 | Contact centre integration | Met | Due 22 Aug 2026 · Completed 21 Aug 2026 |
| Customer portal milestone 40DT-MAIN · DT-302-M040 | Customer portal | Missed | Due 10 Sept 2026 · Completed 13 Sept 2026 |
| Contact centre integration milestone 41DT-MAIN · DT-303-M041 | Contact centre integration | Met | Due 20 Sept 2026 · Completed 19 Sept 2026 |
| Customer data platform milestone 42DT-MAIN · DT-301-M042 | Customer data platform | Met | Due 7 Oct 2026 · Completed 6 Oct 2026 |
| Data model signed offDT-MAIN · DT-301-M043 | Customer data platform | Met | Due 15 Sept 2026 · Completed 14 Sept 2026 |
| Portal accessibility auditDT-MAIN · DT-302-M044 | Customer portal | Missed | Due 4 Oct 2026 · Completed — |
| Depot refurbishment milestone 47DT-C · NF-11-M047 | Depot refurbishment | Met | Due 6 Apr 2026 · Completed 5 Apr 2026 |
| Fleet charging milestone 48DT-C · NF-12-M048 | Fleet charging | Met | Due 14 Apr 2026 · Completed 13 Apr 2026 |
| Fleet charging milestone 49DT-C · NF-12-M049 | Fleet charging | Met | Due 7 May 2026 · Completed 6 May 2026 |
| Warehouse automation milestone 50DT-C · NF-13-M050 | Warehouse automation | Met | Due 16 May 2026 · Completed 15 May 2026 |
| Depot refurbishment milestone 51DT-C · NF-11-M051 | Depot refurbishment | Met | Due 8 Jun 2026 · Completed 7 Jun 2026 |
| Warehouse automation milestone 52DT-C · NF-13-M052 | Warehouse automation | Missed | Due 15 Jun 2026 · Completed 18 Jun 2026 |
| Depot refurbishment milestone 53DT-C · NF-11-M053 | Depot refurbishment | Met | Due 9 Jul 2026 · Completed 8 Jul 2026 |
| Fleet charging milestone 54DT-C · NF-12-M054 | Fleet charging | Met | Due 18 Jul 2026 · Completed 17 Jul 2026 |
| Fleet charging milestone 55DT-C · NF-12-M055 | Fleet charging | Met | Due 5 Aug 2026 · Completed 4 Aug 2026 |
| Warehouse automation milestone 56DT-C · NF-13-M056 | Warehouse automation | Met | Due 17 Aug 2026 · Completed 16 Aug 2026 |
| Depot refurbishment milestone 57DT-C · NF-11-M057 | Depot refurbishment | Met | Due 11 Sept 2026 · Completed 10 Sept 2026 |
| Warehouse automation milestone 58DT-C · NF-13-M058 | Warehouse automation | Met | Due 19 Sept 2026 · Completed 18 Sept 2026 |
| Depot refurbishment milestone 59DT-C · NF-11-M059 | Depot refurbishment | Met | Due 5 Oct 2026 · Completed 4 Oct 2026 |
| Fleet charging milestone 60DT-C · NF-12-M060 | Fleet charging | Met | Due 13 Oct 2026 · Completed 12 Oct 2026 |
| General ledger migration milestone 63DT-MAIN · DT-401-M063 | General ledger migration | Met | Due 5 Apr 2026 · Completed 4 Apr 2026 |
| Procure-to-pay milestone 64DT-MAIN · DT-402-M064 | Procure-to-pay | Met | Due 12 Apr 2026 · Completed 11 Apr 2026 |
| Reporting hub milestone 65DT-MAIN · DT-403-M065 | Reporting hub | Met | Due 19 Apr 2026 · Completed 18 Apr 2026 |
| General ledger migration milestone 66DT-MAIN · DT-401-M066 | General ledger migration | Met | Due 6 May 2026 · Completed 5 May 2026 |
| Procure-to-pay milestone 67DT-MAIN · DT-402-M067 | Procure-to-pay | Met | Due 13 May 2026 · Completed 12 May 2026 |
| Reporting hub milestone 68DT-MAIN · DT-403-M068 | Reporting hub | Met | Due 20 May 2026 · Completed 19 May 2026 |
| General ledger migration milestone 69DT-MAIN · DT-401-M069 | General ledger migration | Met | Due 7 Jun 2026 · Completed 6 Jun 2026 |
| Procure-to-pay milestone 70DT-MAIN · DT-402-M070 | Procure-to-pay | Met | Due 14 Jun 2026 · Completed 13 Jun 2026 |
| Reporting hub milestone 71DT-MAIN · DT-403-M071 | Reporting hub | Met | Due 21 Jun 2026 · Completed 20 Jun 2026 |
| General ledger migration milestone 72DT-MAIN · DT-401-M072 | General ledger migration | Met | Due 8 Jul 2026 · Completed 7 Jul 2026 |
| Procure-to-pay milestone 73DT-MAIN · DT-402-M073 | Procure-to-pay | Missed | Due 15 Jul 2026 · Completed 3 Aug 2026 |
| Reporting hub milestone 74DT-MAIN · DT-403-M074 | Reporting hub | Met | Due 22 Jul 2026 · Completed 21 Jul 2026 |
| General ledger migration milestone 75DT-MAIN · DT-401-M075 | General ledger migration | Met | Due 9 Aug 2026 · Completed 8 Aug 2026 |
| Procure-to-pay milestone 76DT-MAIN · DT-402-M076 | Procure-to-pay | Met | Due 16 Aug 2026 · Completed 15 Aug 2026 |
| Reporting hub milestone 77DT-MAIN · DT-403-M077 | Reporting hub | Met | Due 23 Aug 2026 · Completed 22 Aug 2026 |
| General ledger migration milestone 78DT-MAIN · DT-401-M078 | General ledger migration | Met | Due 10 Sept 2026 · Completed 9 Sept 2026 |
| Procure-to-pay milestone 79DT-MAIN · DT-402-M079 | Procure-to-pay | Met | Due 17 Sept 2026 · Completed 16 Sept 2026 |
| Reporting hub milestone 80DT-MAIN · DT-403-M080 | Reporting hub | Met | Due 24 Sept 2026 · Completed 23 Sept 2026 |
| Reporting hub milestone 81DT-MAIN · DT-403-M081 | Reporting hub | Met | Due 13 Oct 2026 · Completed 12 Oct 2026 |
| Chart of accounts frozenDT-MAIN · DT-401-M082 | General ledger migration | Met | Due 6 Oct 2026 · Completed 5 Oct 2026 |
Exclusions
Records held for review, not linked to a project, not in USD, or without an approved budget.
| Excluded | Reason | Amount |
|---|---|---|
| Tooling licence renewal | Held for review — no plan baseline due date in effect | — |