Overview
Records not loaded — Delivery tracking (second instance)
Connection lost. Figures on this page do not include the latest data from Delivery tracking (second instance) (DT-C). Use Retry on this source in Administration → Data sources.
Forecast over / under budget+840,000USDLoaded at02:00Data as of19 Oct 20264.1% of approved budgetIncludes 10 of 12 projects · Partial (2 missing)On-time rate82%Loaded at09:13Data as of20 Oct 2026StaleMet / Due: 61 / 74Includes 12 of 12 projects · 1 milestone held for reviewOverdue milestones2Loaded at09:13Data as of20 Oct 2026Stale1 criticalIncludes 12 of 12 projectsBlocked work4Loaded at06:50Data as of20 Oct 2026Stale2 high severityIncludes 12 of 12 projectsHigh risks2Loaded at09:56Data as of20 Oct 2026Risk score (likelihood × impact) ≥ 15Includes 12 of 12 projects · 1 risk held for review
On-time rate trend
Met / Due for every milestone due by each month's reporting cutoff. A dashed marker shows where a plan baseline version changes.
Values as text
| -6 | 100% |
|---|---|
| -5 | 95% |
| -4 | 91% |
| -3 | 86% |
| -2 | 85% |
| -1 | 85% |
| This month | 82% |
Forecast variance trend
Forecast over / under budget per month, in USD.
Values as text
| -6 | 292,000 USD |
|---|---|
| -5 | 491,000 USD |
| -4 | 793,000 USD |
| -3 | 780,000 USD |
| -2 | 810,000 USD |
| -1 | 826,500 USD |
| This month | 840,000 USD |
Programme comparison
Programme status is never affected by the owner filter.
| Programme | Status | Triggers | Variance | On-time |
|---|---|---|---|---|
| Network ModernisationMaria Keller | Redpartial data |
| +100,000 USD4.0% · Partial | 70%14 / 20 |
| Customer PlatformTom Reyes | Amber |
| +580,000 USD5.8% | 75%15 / 20 |
| Northern FacilitiesAnna Novak | Stale | None | +10,000 USD0.3% | 93%13 / 14 |
| Finance Systems RenewalJames Okafor | Green | None | +150,000 USD3.0% | 95%19 / 20 |
Top 5 bottlenecks
Blocked work, most severe and longest blocked first.
- High severityAPI contract sign-offCustomer data platform · Priya Nair · Waiting on vendorBlocked 9 days · Tasks waiting on this: 3
- High severityLoad test core switchCore network cutover · Maria Keller · Environment unavailableBlocked 6 days · Tasks waiting on this: 1
- Medium severityChoose flooring supplierDepot refurbishment · Anna Novak · Awaiting decisionBlocked 5 days · Tasks waiting on this: 0
- Medium severityAccessibility fix batchCustomer portal · Tom Reyes · Waiting on vendorBlocked 2 days · Tasks waiting on this: 0
High risks
Risk score (likelihood × impact) 15 or above, open at the cutoff.
- Risk score 16Data residency approval delayedCustomer data platform · Priya Nair · Likelihood 4 × impact 4Legal to issue opinion.
- Risk score 15Cutover window may be refused by operationsCore network cutover · Maria Keller · Likelihood 3 × impact 5Confirm fallback window with operations by day 24.
Partial (1 missing) — open risks without a rating are excluded.